Renovation of the Arts and Letters Sector
Federal contribution
$571,200
Federal share31%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Granby
- Construction start
- May 24, 2021(actual)
- Construction end
- Oct 4, 2021(actual)
Against the original forecast
- Construction end6 weeks lateforecast Aug 20, 2021
Also in Granby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58971 in the federal list. How to read these figures.