Modernization of the operating room and related spaces as well as the emergency sector by adding storage and moving employee spaces, Hôpital de Jonquière
Federal contribution
$1.7M
$1,680,000
Federal share80%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du SaguenayLac-Saint-Jean
- Construction start
- Sep 20, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 30, 2021
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58986 in the federal list. How to read these figures.