Replacement of A-wing ventilation systems (Level 4-5)
Federal contribution
$400,000
Federal share43%
of $927.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Sep 6, 2021(actual)
- Construction end
- Oct 21, 2022(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Sep 20, 2021
- Construction end4 months lateforecast Jun 30, 2022