Replacement of A-wing ventilation systems (Level 4-5)

Trois-Rivières, Quebec

completeVentilationCVRIS
Federal contribution
$400,000
Federal share43%

of $927.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 6, 2021(actual)
Construction end
Oct 21, 2022(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 20, 2021
  • Construction end4 months lateforecast Jun 30, 2022

Also in Trois-Rivières