Upgrade of the electrical input and the emergency power supply system (generators) -Hôpital de la Baie
Federal contribution
$1.3M
$1,288,123
Federal share80%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du SaguenayLac-Saint-Jean
- Construction start
- Oct 8, 2021(actual)
- Construction end
- Nov 3, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 19, 2021
- Construction end10 months lateforecast Dec 20, 2022
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58993 in the federal list. How to read these figures.