Back to projects

Upgrade of the electrical input and the emergency power supply system (generators) -Hôpital de la Baie

Saguenay, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.3M
$1,288,123
Federal share80%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 8, 2021(actual)
Construction end
Nov 3, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 19, 2021
  • Construction end10 months lateforecast Dec 20, 2022