Roof repair on wing # 1-Centre d'hébergement Jacques-Cartier
Federal contribution
$468,000
Federal share80%
of $585.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du SaguenayLac-Saint-Jean
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Nov 8, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2021
- Construction end6 weeks lateforecast Sep 30, 2023