Roof repair on wing # 1-Centre d'hébergement Jacques-Cartier

Saguenay, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$468,000
Federal share80%

of $585.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 2, 2021(actual)
Construction end
Nov 8, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2021
  • Construction end6 weeks lateforecast Sep 30, 2023