Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Jonquière
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Oct 1, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 4, 2021
- Construction end3 months lateforecast Jun 30, 2021
Also in Saguenay