Replacement of the windows in the swimming pool corridor
Federal contribution
$397,981
Federal share52%
of $760.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Jonquière
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Oct 1, 2021(actual)
Against the original forecast
- Construction start7 weeks earlyforecast May 17, 2021
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59005 in the federal list. How to read these figures.