Library retrofit and transformation into an innovative living environment
Federal contribution
$365,300
Federal share16%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Sept-Îles
- Construction start
- Jun 15, 2021(actual)
- Construction end
- May 2, 2022(actual)
Against the original forecast
- Construction end3 months lateforecast Jan 21, 2022
Also in Sept-Îles