Library retrofit
Federal contribution
$1.2M
$1,226,378
Federal share63%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Trois-Rivières
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Apr 29, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Mar 31, 2022
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59015 in the federal list. How to read these figures.