Building D roof retrofit

Saint-Jean-sur-Richelieu, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$145,870
Federal share74%

of $197.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Oct 28, 2021(actual)