Replacement of the condensing boilers (heating), the condensate tank and addition of a ventilation system to the boiler room
Federal contribution
$360,000
Federal share80%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Aug 10, 2021(actual)
- Construction end
- May 8, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 2, 2021
- Construction end2 months lateforecast Feb 25, 2023