Back to projects

Replacement of the condensing boilers (heating), the condensate tank and addition of a ventilation system to the boiler room

Trois-Rivières, Quebec

completeVentilationCVRIS
Federal contribution
$360,000
Federal share80%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 10, 2021(actual)
Construction end
May 8, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 2, 2021
  • Construction end2 months lateforecast Feb 25, 2023

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59070 in the federal list. How to read these figures.