Entrance #19 and masonry retrofits
Federal contribution
$519,722
Federal share80%
of $649.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Trois-Rivières
- Construction start
- May 27, 2022(actual)
- Construction end
- Jul 18, 2023(actual)
Against the original forecast
- Construction end6 months lateforecast Jan 27, 2023