Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Centre
- Construction start
- May 12, 2023(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Dec 1, 2022