Library and Collaborative Space Renovation

Saguenay, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$1.5M
$1,524,800
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Chicoutimi
Construction start
Jun 16, 2021(actual)
Construction end
Nov 19, 2021(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 1, 2021
  • Construction end7 weeks lateforecast Oct 1, 2021

Also in Saguenay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59143 in the federal list. How to read these figures.