Library and Collaborative Space Renovation
Federal contribution
$1.5M
$1,524,800
Federal share80%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Chicoutimi
- Construction start
- Jun 16, 2021(actual)
- Construction end
- Nov 19, 2021(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 1, 2021
- Construction end7 weeks lateforecast Oct 1, 2021
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59143 in the federal list. How to read these figures.