Renovation of premises at the 2000 level of the Pierre-Boucher Pavilion
Federal contribution
$1.0M
$1,040,454
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université du Québec à Trois-Rivières
- Construction start
- Mar 13, 2023(actual)
- Construction end
- Jun 3, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 6, 2023
- Construction end4 months earlyforecast Sep 30, 2024
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59238 in the federal list. How to read these figures.