Marysville Place - Roof Replacement
Federal contribution
$179,200
Federal share80%
of $224.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Sep 28, 2022(actual)
- Construction end
- Nov 25, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast May 31, 2022
- Construction end4 months earlyforecast Apr 10, 2023
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59298 in the federal list. How to read these figures.