Marysville Place - Roof Replacement

Fredericton, New Brunswick

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$179,200
Federal share80%

of $224.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Sep 28, 2022(actual)
Construction end
Nov 25, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast May 31, 2022
  • Construction end4 months earlyforecast Apr 10, 2023