St. James Civic Centre - Facility Expansion

Winnipeg, Manitoba

underwayCultureCCRIS
Federal contribution
$5.3M
$5,288,000
Federal share40%

of $13.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2021
today
2022202420262028
BuiltForecast

Approved 6 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Winnipeg
Construction start
May 12, 2025(actual)
Construction end
Nov 30, 2027(forecast)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 20, 2025

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59353 in the federal list. How to read these figures.