Vision Nursing Home HVAC Upgrade

Sarnia, Ontario

completeVentilationCVRIS
Federal contribution
$351,546
Federal share80%

of $439.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 3, 2021(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction end15 months lateforecast Jul 1, 2022