Idlewyld Manor HVAC Upgrade

Hamilton, Ontario

completeVentilationCVRIS
Federal contribution
$2.2M
$2,214,124
Federal share80%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 5, 2021(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 10, 2021