Southlake Residential Care Village HVAC Upgrade
Federal contribution
$130,686
Federal share80%
of $163.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Southlake Residential Care Village - Southlake Residential Care Village
- Construction start
- Jul 26, 2021(actual)
- Construction end
- Mar 22, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast May 24, 2021
- Construction end12 months lateforecast Mar 31, 2022
Also in Newmarket
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59476 in the federal list. How to read these figures.