Long-Term Care (LTC) Home - HVAC/Isolation/Infection Prevention and Control (IPC) Infrastructure

Espanola, Ontario

completeVentilationCVRIS
Federal contribution
$4.0M
$3,965,474
Federal share80%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022202320242025
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 31, 2021
  • Construction end9 months lateforecast Mar 31, 2024