Mead Boulevard Watermain Replacement

Espanola, Ontario

completeDrinking WaterGIS
Federal contribution
$2.0M
$1,996,291
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
20232024
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Espanola
Construction start
Apr 17, 2023(actual)
Construction end
Oct 18, 2024(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 1, 2023
  • Construction end8 months earlyforecast Jun 30, 2025