Replacement of Building Automation Control System

Shelburne, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$144,000
Federal share80%

of $180.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 19, 2021(actual)
Construction end
Jun 10, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2021
  • Construction end3 months lateforecast Feb 28, 2022