Long-Term Care Home HVAC upgrades
Federal contribution
$132,106
Federal share80%
of $165.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
2022
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Governing Council of the Salvation Army in Canada - R. H. Lawson Eventide Home
- Construction start
- Jul 31, 2021(actual)
- Construction end
- Aug 1, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast May 3, 2021
- Construction end7 months lateforecast Dec 31, 2021
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59515 in the federal list. How to read these figures.