Long-Term Care Home HVAC upgrades

Niagara Falls, Ontario

completeVentilationCVRIS
Federal contribution
$132,106
Federal share80%

of $165.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 31, 2021(actual)
Construction end
Aug 1, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast May 3, 2021
  • Construction end7 months lateforecast Dec 31, 2021