Long-Term Care Home HVAC Upgrades

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$1.3M
$1,258,368
Federal share80%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built
Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Sep 19, 2022(actual)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2022
  • Construction end4 months lateforecast May 30, 2022

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59516 in the federal list. How to read these figures.