HVAC Upgrade

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$596,800
Federal share80%

of $746.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built
Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2022(actual)
Construction end
Nov 10, 2022(actual)

Against the original forecast

  • Construction start14 months lateforecast May 5, 2021
  • Construction end13 months lateforecast Sep 30, 2021