The Pines IPAC Improvements
Federal contribution
$79,200
Federal share80%
of $99.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
2022
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The District Municipality of Muskoka - The Pines
- Construction start
- Jul 15, 2022(actual)
- Construction end
- Sep 25, 2022(actual)
Against the original forecast
- Construction end15 months earlyforecast Dec 31, 2023
Also in Bracebridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59519 in the federal list. How to read these figures.