Enhancements to the HVAC System

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$84,000
Federal share79%

of $105.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 14, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jul 1, 2021
  • Construction end2 years lateforecast Dec 15, 2021