Chiller Unit Replacement

Ottawa, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$108,880
Federal share80%

of $136.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Mar 31, 2022
  • Construction end12 months lateforecast Dec 31, 2022