Back to projects

Long Term Care air conditioning augmentation

St. Catharines, Ontario

completeVentilationCVRIS
Federal contribution
$24,330
Federal share80%

of $30.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 15, 2021(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 3, 2021
  • Construction end20 months lateforecast Jul 17, 2021

Also in St. Catharines