Replace Existing Aging HVAC system

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$351,058
Federal share80%

of $438.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Dec 1, 2021(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 1, 2021
  • Construction end23 months lateforecast Nov 30, 2021