Back to projects

Glen-Stor-Dun Lodge Air Supply Units

Cornwall, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$304,000
Federal share80%

of $380.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 26, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 3, 2021
  • Construction end2 years lateforecast Dec 31, 2021

Also in Cornwall

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59542 in the federal list. How to read these figures.