Facility Upgrades for Health and Safety in Horton

Horton, Ontario

completeOtherCVRIS
Federal contribution
$74,800
Federal share80%

of $93.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Horton
Construction start
Jun 1, 2021(actual)
Construction end
Jan 20, 2023(actual)

Against the original forecast

  • Construction end4 months lateforecast Sep 30, 2022

Also in Horton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59558 in the federal list. How to read these figures.