Stormwater Drainage Study and design of stormwater management facilities(s) to service Lime Kiln Road.

Horton, Ontario

completeWastewaterCWWF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Horton
Construction start
Oct 1, 2017(actual)
Construction end
Apr 30, 2019(actual)

Against the original forecast

  • Construction start2 months earlyforecast Nov 30, 2017
  • Construction end8 months earlyforecast Dec 31, 2019