Rural Road Stormwater Drainage Design & Construction of open ditches and outlet(s) for Humphries Road
Federal contribution
$25,000
Federal share50%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Horton
- Construction start
- Aug 26, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start8 months lateforecast Dec 15, 2016
- Construction end3 months earlyforecast Dec 31, 2019
Also in Horton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49603 in the federal list. How to read these figures.