Back to projects

Lloydminster Agricultural Exhibition Association Limited - Lloydminster Agricultural Exhibition Association COVID 19 Technology & Safety Upgrades

Lloydminster, Saskatchewan

completeVentilationCVRIS
Federal contribution
$104,587
Federal share40%

of $261.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
2022
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 1, 2021(actual)
Construction end
Dec 31, 2021(actual)

Also in Lloydminster

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59580 in the federal list. How to read these figures.