The Pines Long Term Care (LTC) Emergency Generator Upgrade

Bracebridge, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$270,640
Federal share80%

of $338.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 27, 2023(actual)
Construction end
Dec 15, 2023(actual)

Also in Bracebridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59584 in the federal list. How to read these figures.