Upgrades and Repairs to Municipal Buildings
Federal contribution
$3.1M
$3,116,000
Federal share80%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 9, 2021
202220232024
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 30, 2021(actual)
- Construction end
- Oct 17, 2024(actual)
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59585 in the federal list. How to read these figures.