Back to projects

Upgrades and Repairs to Municipal Buildings

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$3.1M
$3,116,000
Federal share80%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 9, 2021
202220232024
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Ottawa
Construction start
Sep 30, 2021(actual)
Construction end
Oct 17, 2024(actual)