Reconstruction of sand storage garage
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Mattice-Val Côté
- Construction start
- Jun 21, 2022(actual)
- Construction end
- Jul 11, 2023(actual)
Against the original forecast
- Construction end8 months lateforecast Nov 18, 2022
Also in Mattice-Val Côté
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59594 in the federal list. How to read these figures.