Mattice - Val Côté Water Treatment Plant Improvements
Federal contribution
$59,800
Federal share40%
of $149.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Mattice-Val Côté
- Construction start
- Jul 14, 2022(actual)
- Construction end
- Oct 31, 2023(actual)
Also in Mattice-Val Côté
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62956 in the federal list. How to read these figures.