Replace sanitary pumps at the Sewage pumping station

Mattice-Val Côté, Ontario

completeWastewaterCWWF
Federal contribution
$21,420
Federal share50%

of $43.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 15, 2018(actual)
Construction end
Nov 15, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Mar 1, 2017
  • Construction end2 weeks earlyforecast Nov 30, 2018

Also in Mattice-Val Côté

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48357 in the federal list. How to read these figures.