Boys and Girls Club Facility 1770 Heatherington Rd

Ottawa, Ontario

completeRecreationCVRIS
Federal contribution
$4.0M
$4,000,000
Federal share80%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 14, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Ottawa
Construction start
Jun 14, 2021(actual)
Construction end
May 5, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 3, 2021
  • Construction end4 months earlyforecast Sep 1, 2022