Roadway and steps rehabilitation
Federal contribution
$320,000
Federal share80%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 23, 2022(actual)
- Construction end
- Dec 15, 2022(actual)
Against the original forecast
- Construction end10 months earlyforecast Oct 30, 2023