Replacement of exterior doors
Federal contribution
$133,036
Federal share80%
of $166.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Jan 17, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 15, 2021
- Construction end5 weeks lateforecast Dec 15, 2021
Also in Blainville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59696 in the federal list. How to read these figures.