Water Treatment Plant Generator Replacement
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Rainy River
- Construction start
- Apr 12, 2021(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start5 weeks earlyforecast May 17, 2021
Also in Rainy River
- Highway 11, Replacement of the Rainy River-Baudette International Bridge at Canada/United States Border$13.1M
- Third Street Water Distribution Upgrades$2.0M
- Rainy River Health Centre(Eldcap) HVAC & Sprinkler$1.2M
- Second Street and Broadway Avenue Rehabilitation$1.1M
- Rehabilitation of Atwood Ave. Water and Waste Water Lines$652.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59714 in the federal list. How to read these figures.