Back to projects

Retrofits, repairs and upgrades for health buildings

Ottawa, Ontario

completeVentilationCVRIS
Federal contribution
$767,577
Federal share80%

of $959.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 10, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Ottawa
Construction start
Jun 14, 2021(actual)
Construction end
Sep 15, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 3, 2021
  • Construction end8 months lateforecast Dec 31, 2022

Also in Ottawa