Retrofits, repairs and upgrades for health buildings
Federal contribution
$767,577
Federal share80%
of $959.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 10, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Sep 15, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 3, 2021
- Construction end8 months lateforecast Dec 31, 2022
Also in Ottawa