Trans-Canada Trail Paving
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Tillsonburg
- Construction start
- Aug 30, 2021(actual)
- Construction end
- Sep 3, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 2, 2021
- Construction end4 weeks lateforecast Aug 6, 2021
Also in Tillsonburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59765 in the federal list. How to read these figures.