Flood Mitigation for Bruce Beach Road

Huron-Kinloss, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Huron-Kinloss
Construction start
Nov 15, 2021(actual)
Construction end
Mar 21, 2022(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Apr 29, 2022