Lucknow Standpipe Replacement
Federal contribution
$1.9M
$1,912,350
Federal share40%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
20232024
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Huron-Kinloss
- Construction start
- Oct 24, 2022(actual)
- Construction end
- Nov 1, 2024(forecast)
Also in Huron-Kinloss
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62814 in the federal list. How to read these figures.