Construction of a new 1,450 m3 elevated drinking water storage tank in the community of Ripley

Huron-Kinloss, Ontario

completeDrinking WaterCWWF
Federal contribution
$317,208
Federal share11%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
201720182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Huron-Kinloss
Construction start
Jan 1, 2017(actual)
Construction end
May 24, 2019(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2017
  • Construction end8 weeks lateforecast Mar 31, 2019