Construction of a new 1,450 m3 elevated drinking water storage tank in the community of Ripley
Federal contribution
$317,208
Federal share11%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
201720182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Huron-Kinloss
- Construction start
- Jan 1, 2017(actual)
- Construction end
- May 24, 2019(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2017
- Construction end8 weeks lateforecast Mar 31, 2019
Also in Huron-Kinloss
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48509 in the federal list. How to read these figures.